After a come to Jesus meeting, finally got the dry wallers on track I think, They put the project behind, their work is good but they had a bit of an issue with showing up. I have ceilings now, and paint on the walls but they still have the master bath and closets to finish.
Got the flooring layout planned and materials selected, carpet and LVL, bought most of the lights and ceiling fans today, think I know what appliances I am going to get but, despite being put "at the top of the priority list" (3 times now) still waiting on the insurance to come across with a contents check.
Bathroom vanities are still up in the air atm, not sure to buy new or try to reuse the old ones. Kitchen cabinets are about a week out from delivery, so I am told.
Had local glass people in Friday to give an estimate on replacing the scratched glass in the sliding door between the house and the sunporch, expect to hear from them Mon or Tues. The old door mostly survived and it is higher quality than I can afford new so I hope to save it.
Forward progress but still a lot of details to nail down and complete. Looking at April to be back in if there are no more big issues.